Mohanlal Mathrani Construction Pvt Ltd. Thor. Authorised Signatory v. The Chief Engineer, Midc
p1-aswp12501-2024.doc AGK
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION WRIT PETITION NO.12501 OF 2024 Mohanlal Matharani Constructions Pvt. Ltd., through authorized signatory Chandan M. Matharani ... Petitioner V/s.
The Chief Engineer, Maharashtra Industrial Development Corporation & Ors.
... Respondents ATUL GANESH KULKARNI ATUL GANESH KULKARNI Date: 2024.10.23 15:54:17 +0530 Mr. Yuvraj Narvankar for the petitioner.
Mr. Prashant Chavan, Senior Advocate with Mr. Meet Vora i/by Navdeep Vora & Associates for respondent Nos.1 to 3.
CORAM
: DEVENDRA KUMAR UPADHYAYA, CJ & AMIT BORKAR, J.
DATED : OCTOBER 23, 2024 P.C.:
1.
Not on board; upon mentioning, taken on board. 2.
On 21st October 2024, the matter was ordered to be placed on board on 19th November 2024. However, it appears that on account of some inadvertence, the interim order granted on 5th September 2024 could not be extended. 3.
Accordingly, we provide that the interim order granted earlier shall continue to operate till the next date of listing.
p1-aswp12501-2024.doc 4.
This order shall be read along with order dated 21st October 2024.
(AMIT BORKAR, J.) (CHIEF JUSTICE)