← Library
Bombay High CourtWP/13976/2024disposed off

Thakur Infraprojects Pvt Ltd v. State Of Maharashtra And ORS

2024-11-12Hon'Ble The Chief Justice , Hon'Ble Shri Justice M. S. Karnik1 pages

902-aswp13976-2024.doc AGK

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION WRIT PETITION NO.13976 OF 2024 Thakur Infraprojects Pvt. Ltd.

... Petitioner V/s.

The State of Maharashtra & Ors.

... Respondents Ms. Nandita Bajpai with Mr. Dhrupad Vaghani & Ashwath Reddy for the petitioner.

Ms. Ekta Dalvi for the applicant in IA/14158/2024. Digitally signed by ATUL GANESH KULKARNI Date:

2024.11.12 15:34:58 +0530 Mr. O.A. Chandurkar, Additional G.P. with Mrs. R.A. Salunkhe, AGP for respondent No.1 - State.

ATUL GANESH KULKARNI

CORAM

: DEVENDRA KUMAR UPADHYAYA, CJ & AMIT BORKAR, J.

DATED : NOVEMBER 12, 2024 P.C.:

1.

It has been stated by the learned counsel for the petitioner that pursuant to the order dated 22nd October 2024, necessary amendments could not be carried out. She prays that one week's further time may be granted to carry out the amendments.

2.

Time, as prayed for, is granted.

3.

Let the amendments pursuant to the order dated 22nd October 2024 be carried out within one week from today. (AMIT BORKAR, J.) (CHIEF JUSTICE)