IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION WRIT PETITION NO.17170 OF 2024 United Builders, Engineers and Government Contractor ... Petitioner V/s.

The State of Maharashtra & Ors.

... Respondents Digitally signed by ATUL GANESH KULKARNI Date:

2024.12.17 14:48:58 +0530 ATUL GANESH KULKARNI Mr. Pranjal Shukla (through V.C.) i/by Mr. Nikhil Adkine for the petitioner.

Mrs. Neha Bhide, Government Pleader with Mr. O.A. Chandurkar, Additional G.P. and Mr.A.R. Deolekar, AGP for respondents-State.

CORAM : DEVENDRA KUMAR UPADHYAYA, CJ & AMIT BORKAR, J.

DATED : DECEMBER 17, 2024 P.C.:

1.

After arguing at some length and when it was pointed out to the learned counsel for the petitioner that for the prayers made in the petition, jurisdiction by this Court under Article 226 cannot be permitted to be exercised; rather the petitioner has remedy of ordinary civil laws, he prays that the petitioner may be permitted to withdraw the writ petition with liberty to seek its remedy before any other appropriate forum/Court.

2.

The writ petition is, thus, dismissed as withdrawn with liberty as prayed for.

(AMIT BORKAR, J.) (CHIEF JUSTICE)