The Executive Engineer, Dhom Balkawadi Project Division v. M/S. Tapi Prestressed Products Ltd
Board Sr.No.:-123
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
APPELLATE SIDE CIVIL JURISDICTION APPEAL FROM ORDER NO. 60 OF 2025 The Executive Engineer, Dhom Balkawadi Project Division ....APPELLANT V/S M/s. Tapi Prestressed Products Ltd ....RESPONDENT WITH INTERIM APPLICATION NO. 1242 OF 2025 In Appeal from Order 60 OF 2025 The Executive Engineer, Dhom Balkawadi Project Division ....PETITIONER V/S M/s. Tapi Prestressed Products Ltd ....RESPONDENT CORAM :
HON'BLE MS. JUSTICE GAURI GODSE J DATE :
11th July, 2025 P.C. :
Balance Daily Board cannot be taken up today on account of paucity of time. Stand Over to 08/10/2025. If any ad-interim / interim relief is operating till today, the same shall continue to operate till the next date. If ad-interim/ interim relief is granted not for a limited period, the same shall remain unaffected. Page 1/2
( FOR REGISTRAR JUDICIAL - I ) Page 2/2