IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION APPEAL FROM ORDER NO. 774 OF 2024 WITH INTERIM APPLICATION NO. 14467 OF 2024 Manali Sharad Shinde ...Appellant

Versus

The Assistant Engineer (Inspection and Maintenance), Municipal Corporation of Gr. Mumbai

...Respondents

SNEHA NITIN CHAVAN **** Mr. Shailesh Redkar i/b Mr. Shailesh Narkar for the Applicant. Mr. Om Suryawanshi for Respondent/Corporation. **** by SNEHA NITIN CHAVAN Date: 2024.11.11 20:20:05 +0530 CORAM :

M.M. SATHAYE, J.

DATE :

11 NOVEMBER 2024 P.C. :

1.

Not on Board. Taken on Board by way of production. 2.

Learned Counsel for the Appellant / Plaintiff invited this Court's attention to the order dated 18.10.2024 by which the Respondent/Municipal Corporation was directed not to take coercive action and not to act upon the impugned notice dated 15.10.2024 in respect of the suit premises for a period of three weeks. Three weeks have expired on 08.11.2024 which was Friday.

3.

Today, learned counsel for the Respondent/Municipal Corporation submits that he has no clear instructions that the demolition has already taken placed.

Sneha Chavan 1/2

2 501 ao 774-24.doc 4.

In that view of the matter, place this Appeal from Order for admission on 25.11.2024. Till then, interim protection granted by the Trial Court on 18.10.2024 shall continue.

(M.M. SATHAYE, J.) Sneha Chavan 2/2