The Executive Engine Medium Project Anand Nagar Osmanabad v. Chandrakant Kashinath Kalshite And ORS
1 1000 ca 997.25
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 997 OF 2025 IN FIRST APPEAL STAMP NO. 31712 OF 2024 The Executive Engineer Medium Project Anand Nagar Osmanabad .. Applicant
Versus
Chandrkant Kashinath Kalshite and others .. Respondents Shri Rahul A. Tambe, Advocate for the Applicant. Shri B. A. Shine, A.G.P., for the Respondent Nos. 2 and 3. CORAM : SHAILESH P. BRAHME, J.
DATE : 18TH JUNE, 2025.
ORDER :
.
Learned counsel Mr. Tambe submits that more time is required for depositing the amount. Further period of eight (08) weeks is granted for depositing the amount.
2.
Interim relief shall continue till that period. If amount is not deposited within extended period, interim relief granted shall stand vacated automatically without further reference to this Court. Stand over to 13.08.2025.
[ SHAILESH P. BRAHME J. ] bsb/June 25