IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD.

986 CIVIL APPLICATION NO.6455 OF 2024 IN FAST/14144/2024 The Regional Manager, The New India Insurance Corrected Assurance Company Ltd ..Applicant

Versus

Daivshala Dileeprao Ghadge and Others ..Respondents .....

Advocate for Applicant : Mr. Ramesh Ramdas Imale Advocate for Respondents No.1 to 3 : Mr. Shrimant Mundhe AGP for Respondent No.4 / State : Mr. A.D. Wange .....

CORAM : R. G. AVACHAT AND NEERAJ P. DHOTE, JJ.

Dated :

July 26, 2024 PER COURT :- .

This is the Application for condonation of 103 days delay in preferring the Appeal against the Judgment and Order dated 17.10.2023 passed by Motor Accident Claims Tribunal, Ambajogai in Motor Accident Claim Petition No.17/2019.

2.

Issue notice to the Respondents, returnable on 09.08.2024. Learned Advocate Mr. Shrimant Mundhe waives service for Respondents No.1 to 3 and learned AGP waives service for Respondent No.4 / State. ( NEERAJ P. DHOTE, J. ) ( R. G. AVACHAT, J. ) GGP Signed by: Gajanan G. Punde Designation: PA To Honourable Judge Date: 30/07/2024 11:15:13