The Executive Engineer Director Godawari Marathwada Irrigation Devlopment Corporation Aurangabad v. The State Of Maharashtra Thr Collector, Jalna And ORS
2026:BHC-AUG:3593 1 68 ca 6613.24
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 6613 OF 2024 IN FIRST APPEAL STAMP NO. 11039 OF 2024 Executive Engineer Director, Godavari Marathwada Irrigation Development Corporation Aurangabad .. Applicant
Versus
The State of Maharashtra, through Collector Jalna and others .. Respondents Shri Shivraj B. Kadu, Advocate for the Applicant. Shri N. D. Raje, A.G.P. for the Respondent Nos. 1 and 2. Shri Durgesh M. Pingale, Advocate for the Respondent Nos. 4 to 6. CORAM : SHAILESH P. BRAHME, J.
DATE : 27TH JANUARY, 2026.
FINAL ORDER :
.
Heard both sides.
2.
The applicant - acquiring body seeks to condone delay of 675 days caused in preferring first appeal. There is no serious contest to the application.
3.
For the reasons stated in the application, it is desirable to condone the delay. The civil application is allowed. The delay stands condoned. Office shall register the first appeal. The civil application is disposed of.
[ SHAILESH P. BRAHME J. ] bsb/Jan. 26