The Executive Engineer, Minor Irrigation Division Osmanabad v. Subabai Bhagwan Kale And Others
2026:BHC-AUG:2529 1 61 ca 7282.24
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 7282 OF 202_4 IN FIRST APPEAL STAMP NO. 12615 OF 2024 The Executive Engineer, Minor Irrigation Division Osmanabad .. Applicant
Versus
Subabai Bhagwan Kale Since deceased through her L.Rs.
Rama Bhagwan Kale and others .. Respondents Ms. Vaishali S. Swami, Advocate h/f Shri Mahesh C. Swami, Advocate for the Applicant.
Shri Dinesh D. Daund, Advocate h/f Shri Manoj D. Shinde, Advocate for the Respondent Nos. 1A to 1E.
Shri S. V. Hange, A.G.P. for the Respondent Nos. 2 and 3. CORAM : SHAILESH P. BRAHME, J.
DATE : 20TH JANUARY, 2026.
FINAL ORDER :
.
Applicant - acquiring body seeks condonation of delay of 323 days caused in preferring appeal. For the reasons stated in the application it is desirable to condone the delay. 2.
The averments in the application have not been controverted by the respondents. There are no malafides on the part of the applicant to prefer the appeal belated. 3.
For the reasons stated in the application the civil
2 61 ca 7282.24 application is allowed. The delay is condoned. Office shall register the first appeal. The civil application is disposed of. [ SHAILESH P. BRAHME J. ] bsb/Jan. 26