Bombay High CourtCA/10279/2024allowed to be withdrawn at admission stage

The Executive Engineer Irrigation Project Strengthening Division Omerga Osmanabad v. Anil Keshavrao Deshpande And ANR

2025-04-28Hon'Ble Shri Justice S. G. Chapalgaonkar1 pages

2025:BHC-AUG:12639

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 55 CIVIL APPLICATION NO. 10279 OF 2024 IN FAST/25267/2024 The Executive Engineer Irrigation Project Strengthening Division Omerga Osmanabad

VERSUS

Anil Keshavrao Deshpande And Anr ...

Advocate for Applicant : Mr. Avishkar Sukhdeo Shelke AGP for Respondents: Mr. D B Bhange Advocate for Respondent1 : Mr. K.B. Jadhav h/f P.B. Rakhunde ...

CORAM : S. G. CHAPALGAONKAR, J.

Dated : April 28, 2025 PER COURT :- 1.

Heard learned advocates appearing for the respective parties.

2.

The applicant seeks to condone the delay of 436 days caused in filing the appeal.

3.

Perused reasons as stated in the application. Apparently, delay is occasioned on account of administrative exigencies and procedural aspects required to be complied with by the applicant. Hence, applicant has not derived any advantage by making such delay. In the result, sufficient cause is made out. Hence, application is allowed in terms of prayer clause 'B' and disposed of.

( S. G. CHAPALGAONKAR, J. ) ...