Bombay High CourtCA/11497/2024admittedallowedgrantedrule absolute

The Executive Engineer Medium Project Anand Nagar Osmanabad And ORS v. Madhav Tukaram Mane Died His Lrs Kalpana Shivaji Jadhav And ORS

2025-04-29Hon'Ble Shri Justice S. G. Chapalgaonkar1 pages

{1} 909 sr.no..odt

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO. 11497 OF 2024 IN FAST/26870/2024 The Executive Engineer Medium Project Anand Nagar Osmanabad And Ors ....Applicant

VERSUS

Madhav Tukaram Mane Died His Lrs Kalpana Shivaji Jadhav And Ors .....Respondent .....

Advocate for Applicant : Mr. Gulab Balbhim Rajale CORAM : S.G. CHAPALGAONKAR, J.

DATE : 29th APRIL, 2025.

P.C. :- 1.

Heard Mr. Rajale, learned advocate for applicant. 2.

Applicant seeks to condone delay of 525 days in filing the appeal. Perused the application and reasons stated therein. Apparently, delay has occasioned on account of administrative reasons and procedural compliances. Although notice of this application is served upon the respondents, none appears.

3.

IN that view of the matter, sufficient cause is made out. IN the result, application is allowed. Delay is condoned. Appeal be registered subject to removal of office objections. [S.G. CHAPALGAONKAR, J.] grt/-