The Executive Engineer Minor Irrigation Division Lataur Through Gmidc Aurangabad v. Babu Gyana Malge
2025:BHC-AUG:12635 CA 13130.24+.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 58 CIVIL APPLICATION NO. 13130 OF 2024 IN FAST/29103/2024 The Executive Engineer Minor Irrigation Division Latur Through G.m.i.d.c. Aurangabad And Ors
VERSUS
Pradip Dajisaheb Patil ...
WITH CIVIL APPLICATION NO. 13131 OF 2024 IN FAST/29103/2024 ...
WITH CIVIL APPLICATION NO. 13132 OF 2024 IN FAST/29106/2024 WITH CIVIL APPLICATION NO. 13133 OF 2024 IN FAST/29106/2024 WITH CIVIL APPLICATION NO. 13134 OF 2024 IN FAST/29109/2024 WITH CIVIL APPLICATION NO. 13135 OF 2024 IN FAST/29109/2024 ...
AND 59 CIVIL APPLICATION NO. 13720 OF 2024 IN FAST/32332/2024 The Executive Engineer Minor Irrigation Division Lataur Through Gmidc Aurangabad
VERSUS
Babu Gyana Malge ...
WITH CIVIL APPLICATION NO. 13721 OF 2024 IN FAST/32332/2024 WITH CIVIL APPLICATION NO. 13722 OF 2024 IN FAST/32335/2024 WITH CIVIL APPLICATION NO. 13723 OF 2024 IN FAST/32335/2024 ...
Advocate for Applicant : Mr. A N Gaddime Advocate for Respondent 1 : Mr. N.D. Kendre
CA 13130.24+.odt CORAM : S. G. CHAPALGAONKAR, J.
Dated : April 28, 2025 ORDER :- Delay Applications :- 1.
Heard learned advocates appearing for the respective parties.
2.
The applicant seeks to condone the delay caused in filing the appeal/s.
3.
Learned advocate appearing for the respondent/original claimant vehemently opposed the application.
4.
Perused the reasons as recorded in the applications. Delay is occasioned on account of administrative exigencies and procedural aspects of the matter. No malafides are attributed against the applicant/s. Applicants have not derived any advantage by making such delay. Hence, sufficient cause is made out to condone the delay. In the result, applications are allowed. Delay caused in filing the appeal/s is condoned. Civil applications stand disposed of.
5.
Appeals be registered subject to removal of office objections.
6.
First Appeals and stay applications are adjourned after eight weeks.
( S. G. CHAPALGAONKAR, J. ) aaa/- ....