Chandan Mohanlal Mathrani Thr. Mohanlal Mathrani Construction Pvt Ltd v. Chief Engineer Pune Zone
528-ARP-117-2024.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION ARBITRATION PETITION No. 117 OF 2024 SHRADDHA KAMLESH TALEKAR Chandan Mohanlal Mathrani through Mohanlal Mathrani Construction Pvt. Ltd.
...Petitioner
Versus
Chief Engineer, Pune Zone
...Respondent
SHRADDHA KAMLESH TALEKAR Date: 2025.03.15 17:49:27 +0530 Mr. Yuvraj Narvankar, for Petitioner.
None for Respondent.
CORAM : SOMASEKHAR SUNDARESAN, J.
Date : March 10, 2025 P. C.
1.
As a last chance to the Respondent to present its say, list under the caption, "Directions" on March 17, 2025 on the Supplementary Board. 2.
All actions required to be taken pursuant to this order, shall be taken upon receipt of a downloaded copy as available on this Court's website. [ SOMASEKHAR SUNDARESAN, J.] March 10, 2025 Shraddha