1 16 wp 3257-2024

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH : NAGPUR WRIT PETITION NO.3257/2024 Adani Infrastructure Management Service Ltd., through its Manager Abhinav Vinodkumar Patil Vs.

Kamal s/o Sonumal Bhati and others - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Shri M.V. Rai, Advocate for petitioner Shri A.V. Pawar, Advocate h/s Shri S.S Katkar, Advocate for respondent No. 1 Shri B.M. Lonare, AGP for respondents/State CORAM :

SMT. M.S. JAWALKAR, J.

DATED : 17.03.2025 Shri A.V. Pawar, learned Counsel holding for Shri S.S. Katkar, learned Counsel appearing for respondent No.1 seeks two weeks' time to file reply. 2.

The record shows that on various occasions, Counsel representing for respondent No.1 has changed. As such, two weeks' time is granted by way of last chance. List the matter on 07.04.2025. 3.

The Assistant Commissioner of Labour, Akola shall adjourn the proceedings in Application (I.D.A.) No.7/2024 beyond 07.04.2025.

JUDGE R.S. Sahare Signed by: Mrs. Ranjana Sahare Designation: PA To Honourable Judge Date: 17/03/2025 17:58:55