V. I. D. C. Through Its Executive Engineer, Minor Irrigation Department, Washim v. Sitaram Bhika Jadhav And Another
2024:BHC-NAG:5514 -1- 20.CAF.1214.2024.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH AT NAGPUR C IVIL APPLICATION (CAF) NO.
OF 2024 IN FIRST APPEAL NO. 1163 OF 2018 VIDC, through its Executive Engineer Vs.
Sitaram Bhika Jadhao & Anr.
********************************************************************************************** Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders ********************************************************************************************** Mr. Anoopsingh Parihar, Advocate for the Appellant. Mr. N.M. Kolhe, Advocate for Respondent No.1. Ms. Sonia Thakur, AGP for Respondent No.2.
CORAM : G. A. SANAP, J.
DATED : 7 th MAY, 2024.
.
Heard learned advocates for the parties.
2.
This is an application by respondent No.1 for withdrawal of the balance amount of compensation lying deposited in this Court.
3.
In view of the facts stated in the application, the application is allowed. Respondent No.1 is allowed to withdraw the balance amount of compensation lying deposited before this Court with accrued interest.
4.
The application stands disposed of, accordingly. (G. A. SANAP, J.) Vijay Signed by: Mr. Vijay Kumar Designation: PA To Honourable Judge Date: 08/05/2024 19:16:43