Baban Jagannath Mhaske v. The Municipal Corporation Of Greater Mumbai
20 Ia-91-2025.doc IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO. 91 OF 2025 IN FIRST APPEAL st. NO. 35183 OF 2024 Baban Jagannath Mhaske.
...Appellant.
Versus
Municipal Corporation of Greater Mumbai
...Respondent.
------ Nidhi Dotiya and Shweta R. Rathod i/b Elixir Legal Services for the Appellant. Ms. Pallavi Khare for the Respondent-Corporation. ------ Coram : Sharmila U. Deshmukh, J.
Date : January 9, 2025.
P. C. :
1.
Interim Application has been preferred seeking condonation of delay of 19 days caused in preferring the First Appeal. 2.
Learned Counsel appearing for the Appellant submits that the certified copy was received on 23rd October 2024, however, due to personal difficulties, the Appellant could not approach the Advocate immediately and therefore there is delay of 19 days. 3.
Learned Counsel appearing for the Respondent opposes the Application by submitting that the explanation is not sufficient. 4.
Considering the short delay of 19 days which has been sufficiently explained in paragraph no.5, I am inclined to condone the delay. Interim Application is allowed.
5.
List the First Appeal for admission on 22nd January 2025. [Sharmila U. Deshmukh, J.] Patil-SR 1 of Signed by: Sachin R. Patil Designation: PS To Honourable Judge Date: 09/01/2025 20:30:01