← Library
Bombay High CourtIA/382/2025disposed off

Central Railway Through The Deputy Chief Engineer (Construction) v. Gajanan Mahadu Pawar (Deceased) Thr. Lrs. 1- A Anusaya Gajanan Pawar And ORS.

2025-01-13Hon'Ble Justice Sharmila U. Deshmukh1 pages

44 Ia-382-2025.doc IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO.382 OF 2025 IN FIRST APPEAL (St.) NO. 30837 OF 2024.

Central Railway, Through the Deputy Chief Engineer (Construction), Panvel Railway Station, District Raigad.

...Applicant.

Versus

Gajanan Mahadu Pawar (deceased) through LRs and Others.

...Respondents.

------ Ms. Leena Patil for Appellant.

Ms. Deepa Punde i/b Mr. Sachin Punde for Respondent Nos.1A to 1F. Mr. A. R. Patil, AGP for Respondent-State.

------ Coram : Sharmila U. Deshmukh, J.

Date : January 13, 2025.

P. C. :

1.

Interim Application has been preferred seeking condonation of delay of 66 days caused in preferring the First Appeal. 2.

The proceedings arise out of land acquisition proceedings. 3.

Learned counsel appearing for Respondent-original claimant does not seriously oppose the Application. Considering that the delay has been properly explained, the Interim Application is allowed. 4.

Delay stands condoned.

[Sharmila U. Deshmukh, J.] Sairaj 1 of