19 Ia-700-2025.doc IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO. 700 OF 2025 IN FIRST APPEAL (St.) NO. 29589 OF 2024 IN L.A.R. NO. 47 OF 2017.

The Executive Engineer, Minor Irrigation, Sangli ...Applicant.

Versus

Sunanda Appasaheb Birajdar and Another

...Respondents.

------ Mr. Sachin Gite for Appellant.

Mr. A. R. Patil, AGP for Respondent-State.

------ Coram : Sharmila U. Deshmukh, J.

Date : 6th March, 2025.

P. C. :

1.

Interim Application has been preferred seeking stay of the impugned judgment and award dated 13th March, 2023. 2.

Learned counsel appearing for Applicant-acquiring body, on instructions, submits that the entire decretal amount along with accrued interest will be deposited in the Reference Court within a period of eight weeks from today.

3.

The statement is accepted as undertaking given to this Court. 4.

In light of the submission made as regards the deposit, adinterim relief in terms of prayer clause 'b'. 5.

Stand over to 5th May, 2025.

[Sharmila U. Deshmukh, J.] Sairaj 1 of