← Library
Bombay High CourtIA/2148/2024disposed off

Gulistan Shah Saqlian Co-Op Housing Society Ltd., Mumbai v. M/S. Gazi Construction, Mumbai And ANR

2025-01-23Hon'Ble Justice Sharmila U. Deshmukh1 pages

88-IA-2148-2024.doc IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO. 2148 OF 2024.

IN FIRST APPEAL NO. 1244 OF 2011.

Gulistan Shah Saqlian Co-Op Housing Society Ltd., Mumbai ...Applicant.

Versus

M/S. Gazi Construction, Mumbai And Anr

...Respondents.

------ Adv. M. V. Holamagi for the Applicant.

Mr. N. K. Dubey i/by V. T. Dubey for the Respondents. ------ Coram : Sharmila U. Deshmukh, J.

Date : January 23, 2025.

P. C. :

1.

Let the copy of Interim Application be served upon the Original Appellant before the next date.

2.

List the matter on 10th February, 2025.

[Sharmila U. Deshmukh, J.] TALLE SHUBHAM ASHOKRAO TALLE SHUBHAM ASHOKRAO Date: 2025.01.27 19:48:10 +0530 Shubham Talle 1 of