Surana Construction (Chembur) Through Its Partner Surendra Surana v. Sandeep S Oberai And ANR
by MULEY SHUBHAM PRAVINRAO Date:
2025.12.19 12:42:42 +0530 MULEY SHUBHAM PRAVINRAO 8-IA-4175-2025.DOCX Shubham
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO. 4175 OF 2025 IN SECOND APPEAL (ST) NO. 24211 OF 2024 Surana Construction (chembur) Through Its Partner Surendra Surana ...Applicant
Versus
Sandeep S Oberai & Anr.
...Respondents
WITH SECOND APPEAL (ST) NO. 24211 OF 2024 ----------------- None for the parties.
----------------- CORAM : ADVAIT M. SETHNA, J.
DATED : 19 DECEMBER 2025 P.C.:- 1.
None appears for the Applicant/Appellant. There appears to be a delay of 8 days in filing the Second Appeal. However, as none appears for the Applicant/Appellant, the Court is unable to pass any further orders on the Interim Application for condonation of delay. 2.
Place these proceedings on 24 December 2025 to give an opportunity to the Applicant/Appellant to be represented, failing which appropriate orders shall be passed.
(Advait M. Sethna, J.)