Bombay High CourtIA/11618/2024disposed off

Prakash Laxman Prajapati And ORS v. Jayesh Hiraman Mhatre

2024-08-12Hon'Ble Justice Kamal Khata , Hon'Ble Shri Justice M.S. Sonak2 pages

by LAXMIKANT GOPAL CHANDAN Date:

2024.08.12 18:15:43 +0530

(5) WP-7943.22-AW-IA-11618.24.DOCX LAXMIKANT GOPAL CHANDAN lgc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION WRIT PETITION NO. 7943 OF 2022 Jayesh Hiraman Mhatre

...Petitioner

Versus

Kalyan Dombiwali Municipal Corporation Through its Commissioner and ors.

...Respondents

WITH INTERIM APPLICATION NO.11618 OF 2024 IN WRIT PETITION NO.7943 OF 2022 Mr Suhas S Deokar, for the Petitioner.

Mr Pradip Patil, for the Respondent Nos. 1 & 2 - KDMC. Mr Chandrakant Jagtap, Asstt. Commissioner & Ward Officer, 10E ward present.

CORAM

M.S. Sonak & Kamal Khata, JJ.

DATED:

12 August 2024 PC:- 1.

Compliance report is filed by the Kalyan Dombiwali Municipal Corporation ("KDMC") stating that the demolition process has started. The learned counsel for the KDMC states that the process would be completed within two weeks from today. 12 August 2024

(5) WP-7943.22-AW-IA-11618.24.DOCX 2.

The time for compliance is accordingly extended up to 26 August 2024. The KDMC must file further compliance report along with photographs in this Court by 30 August 2024. 3.

List the matter on 02 September 2024 to consider the compliances.

(Kamal Khata, J) (M.S. Sonak, J) 12 August 2024