Rahul S/O Ambadas Waykhinde v. The State Of Maharashtra Thr Secrraty Dept. Of Tribal Development And ANR
73-ia-12952-2024.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO. 12952 OF 2024 IN WRIT PETITION (ST) NO. 23192 OF 2022 Rahul S/o Ambadas Waykhinde .....Applicant In the matter between Rahul S/o Ambadas Waykhinde .....Petitioner Vs.
The State of Maharashtra Through Secretary, Department of Tribal Development & Ors.
.....Respondents Mr. Salil Choudhari, i/b Mr. Deepak Choudhari, for the Applicant/Original Petitioner.
Mrs. S.S.Bhende, AGP for Respondent-State.
CORAM : REVATI MOHITE DERE & DR. NEELA GOKHALE, JJ.
DATE : 16th JUNE 2025.
P.C.:- 1.
By this Interim Application, the Applicant seeks restoration of aforesaid Writ Petition to its original file. Delay, if any, is also sought to be condoned.
2.
Perused the Application. It appears that the aforesaid Writ Shivgan 1/2
73-ia-12952-2024.doc Petition came to be dismissed for non-removal of office objections. The reason for not removing the office objections has been set out in paragraph 3 of the Application. Having perused the said paragraph, we find that 'Sufficient Cause' has been made out for restoration of the Writ Petition to its original file.
3.
Accordingly, the Application is allowed and the aforesaid Writ Petition is restored back to its original file. Delay, if any, is also condoned.
4.
Office objections to be removed within three weeks from today.
5.
If office objections are removed, place the Writ Petition for Admission on 14th July 2025..
6.
Interim Application is disposed of.
(DR. NEELA GOKHALE, J.) (REVATI MOHITE DERE, J.) Digitally signed by SHAMBHAVI NILESH SHIVGAN Date:
2025.06.18 20:54:56 +0530 SHAMBHAVI NILESH SHIVGAN Shivgan 2/2