CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO. 15561 OF 2024 IN FIRST APPEAL (ST) NO. 31594 OF 2024 Central Railway ...Applicant Vs.

Joma Nama Patil & Anr.

...Respondents

----------------- Adv. Jenish Jain i/by U. P. Warunjikar for the Applicant. Adv. Sachin S. Punde for Respondent Nos.1A, 1C and 1D. ----------------- CORAM : ARIF S. DOCTOR, J.

DATE : 13TH DECEMBER, 2024 P.C.:- 1.

The captioned Interim Application No.15561 of 2024 is filed for condonation of delay of 186 days in filing the present Appeal. 2.

Learned Counsel for the Applicant submits that the Applicant is a Government body and required various sanctions and approvals before the Appeal could be filed. He submits that the delay has been caused while obtaining the sanctions and approvals.

3.

Learned Counsel for the Respondents does not oppose the Application.

Shubham 1/2

2 25-IA-15561-2024.doc 4.

Hence, Interim Application is allowed and the delay of 186 days is condoned.