← Library
Bombay High CourtARBP/110/2025disposed off

Relcon Infraprojects Ltd v. Bhagwandas Gupta

2025-03-27Hon'Ble Justice Sharmila U. Deshmukh1 pages

514-ARBP-110-2025.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION NO. 110 OF 2025 Digitally signed by SHRADDHA KAMLESH TALEKAR Date:

2025.04.08 20:23:05 +0530 SHRADDHA KAMLESH TALEKAR Relcon Infraprojects Ltd.

...Petitioner

Versus

Bhagwandas Gupta & Ors.

...Respondents

Ms. Aneesa Cheema a/w. Shriya Mehta i/b Akanksha Mishra, for Petitioner.

Ms. Deepanjali Mishra i/b Anita Adsul, for Respondent No. 3. CORAM : SOMASEKHAR SUNDARESAN, J.

Date : March 27, 2025 P. C.

1.

This is a Petition under Section 34 of the Arbitration and Conciliation Act, 1996.

2.

Learned Counsel for the Petitioner submits that all the Respondents have been served. Let reply affidavit be filed no later that April 25, 2025. Rejoinder, if any, no later than May 2, 2025. List the matter on May 5, 2025 on the Production Board.

3.

All actions required to be taken pursuant to this order, shall be taken upon receipt of a downloaded copy as available on this Court's website. [ SOMASEKHAR SUNDARESAN, J.] March 27, 2025 Shraddha