Jayanti Girdharlal Chudasama v. Scale Age Engineering Co. Through Its Partner

2025-01-21Hon'Ble Shri Justice Somasekhar Sundaresan2 pages

10-ARBP-311-2024.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION NO. 311 OF 2024 Jayanti Girdharlal Chudasama & Ors

...Petitioners

Versus

Scale Age Engineering Co. through its partner & Ors

...Respondents

Mr. Sachin A. Mhatre, a/w Yogesh S. Naidu, h/f Mhatre Law Associates, for the Petitioners.

Mr. Ashwin Singh, a/w Siddhhi Vadake, for Respondent No.2.

CORAM

: SOMASEKHAR SUNDARESAN, J.

DATE : JANUARY 21, 2025 PC :

1.

This is a Petition under Section 29-A of the Arbitration and Conciliation Act, 1996 ("the Act").

2.

Today, when the matter is called out, parties jointly request for a short extension of mandate of the arbitral tribunal by four weeks since they are on the verge of a settlement. If the mandate is so extended, they submit, they will be able to place their settlement before the arbitral tribunal and conclude the disputes between them. ASHWINI JANARDAN VALLAKATI 3.

In these circumstances, this Petition is finally disposed of ASHWINI JANARDAN VALLAKATI Date: 2025.01.29 17:59:00 +0530 January 21, 2025 Ashwini Vallakati

10-ARBP-311-2024.doc extending the mandate of the arbitrator by a period of four weeks from today i.e. until February 20, 2025.

4.

All actions required to be taken pursuant to this order shall be taken upon receipt of a downloaded copy as available on this Court's website.

[ SOMASEKHAR SUNDARESAN, J.] January 21, 2025 Ashwini Vallakati