Mahendra Ramniklal Shah v. M/S Gangar Infrastructure
905.ARBP.353.2024.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION NO.353 OF 2024 Mahendra Ramniklal Shah ....Petitioner
Versus
M/S. Gangar Infrastructure ....Respondent Ms Henna P. Shah, Advocate for Petitioner.
Ms Vidhisha Rohia a/w. Princee Vaishnav & Pratik Jani i/b. Prime Legam, Advocates for Respondent.
CORAM: SOMASEKHAR SUNDARESAN, J.
DATE : APRIL 24, 2025 PC :
1.
Stand over to May 2, 2025 on the Supplementary Board since it is earnestly suggested by Learned Counsel on behalf of the Respondent that the matter would be worked out within a week. 2.
All actions required to be taken pursuant to this order, shall be taken upon receipt of a downloaded copy as available on this Court's website.
[ SOMASEKHAR SUNDARESAN, J.] by AARTI GAJANAN PALKAR Date:
2025.04.25 16:37:46 +0530 AARTI GAJANAN PALKAR APRIL 24, 2025 Aarti Palkar