Taufiqua Habib Ansari v. Dudhwala Real Estate And Investment Through Its Partners
by LAXMIKANT GOPAL CHANDAN Date:
2024.07.02 10:15:25 +0530
(65) WP-3180.24.DOCX LAXMIKANT GOPAL CHANDAN lgc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION WRIT PETITION NO. 3180 OF 2024 Taufiqua Habib Ansari and anr
...Petitioners
Versus
Dudhwala Real Estate and Investment Through its Parnters and ors.
...Respondents
Mr Mujahid Ansari, for the Petitioner.
Mr Yohaan Shah i/by Negandhi Shah & Himaytullah, for the Respondent Nos. 1 to 3.
CORAM
M.S. Sonak & Kamal Khata, JJ.
DATED:
01st July 2024 PC:- 1.
Learned counsel for the Respondent Nos. 1 to 3 (Builders/Developers) seeks time upto 15th July 2024 to file a reply or to obtain instructions on why the transit rents are not being paid to the Petitioner.
2.
Respondent Nos.1, 2 and 3 to seek instructions as to why PAAA agreement is not yet executed with the Petitioner. 3.
Stand over to 18th July 2024.
(Kamal Khata, J) (M.S. Sonak, J) 01st July 2024