Bombay High CourtWP/4032/2024disposed off

Kalyan Toll Infrastructure Ltd. v. Muncipal Corporation Greater Mumbai

2024-08-28Hon'Ble The Chief Justice , Hon'Ble Shri Justice M. S. Karnik2 pages

406-WP-4032-2024 Pdp

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION WRIT PETITION NO. 4032 OF 2024 Kalyan Toll Infrastructure Ltd.

.. Petitioner

Versus

Municipal Corporation of Greater Mumbai & Ors.

.. Respondents Dr. Abhinav Chandrachud a/w Ms. Neha Bhosale, Ms. Disha Parekh and Ms. Anuja Divadkar i/by NDB Law for petitioner. Mr. Oorja Dhond i/by Mr. S. K. Sonawane for respondent nos.1 and 2-BMC.

Smt. Jaymala J. Ostwal, Addl. Govt. Pleader for respondent no.3 - State.

Digitally signed by PRAVIN DASHARATH PANDIT Date:

2024.08.28 15:14:37 +0530 PRAVIN DASHARATH PANDIT CORAM: DEVENDRA KUMAR UPADHYAYA, CJ. & AMIT BORKAR, J.

DATE:

28th AUGUST, 2024 P.C.:

1.

On the oral prayer made by the learned counsel for the petitioner, let respondent no.3 be deleted from the array of respondents. Re-verification is dispensed with. 2.

Necessary amendment shall be incorporated by the learned counsel for the petitioner during the course of the day.

3.

Issue notice to the respondents.

4.

Ms. Dhond, learned counsel has put in appearance on behalf of respondent nos.1 and 2 and waives service of notice. She may file affidavit-in-reply within four weeks. Two weeks'

406-WP-4032-2024 time thereafter shall be available to the petitioner to file rejoinder-affidavit, if any.

5.

Stand over to 11th October, 2024.

6.

In the meantime, the petitioner is permitted to move necessary Interim Application for adding certain prayers. (AMIT BORKAR, J.) (CHIEF JUSTICE)