Mbpl-Kec Jv v. Maharashtra Rail Infrastructure Development Corportion Ltd.
41-CARAP-151-2024.DOC Shephali
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION COMMERCIAL ARBITRATION APPLICATION NO.151 OF 2024 MBPL-KEC JV ...Applicant
Versus
Maharashtra Rail Infrastructure Development
...Respondent
Corporation Ltd Mr Sunip Sen, with Anuj Athalya, Nitiin Jain & Rohan Gupta, i/b Legasis Partners, for the Applicant.
Mr Manoj Badgujar, for the Respondent.
CORAM:
ARIF S. DOCTOR, J DATED:
26th September 2024 SHEPHALI SANJAY MORMARE PC:- SHEPHALI SANJAY MORMARE Date: 2024.09.26 17:40:12 +0530 1.
Learned Counsel appearing on behalf of the Respondent Seeks time to file Affidavit in Reply. He also undertakes to file vakalatnama. 2.
Affidavit in Reply to be filed and served on or before 15th October 2024. Affidavit in Rejoinder, if any, to be filed and served on or before 21st October 2024.
3.
List the matter on 24th October 2024.
(ARIF S. DOCTOR, J)