Vibha Amit Gupta v. The General Manager Central Railway
23.CARAP.271.2024.doc sIN THE HIGH COURT OF JUDICATURE AT BOMBAY ORDINARY ORIGINAL CIVIL JURISDICTION COMMERCIAL ARBITRATION APPLICATION NO.271 OF 2024 Vibha Amit Gupta ...Applicant
Versus
The General Manager Central Railway
...Respondent
Mr. C.K. Tripathi, Advocate for Applicant.
Ms Anamika Malhotra, Advocate for Respondent. CORAM: SOMASEKHAR SUNDARESAN, J.
DATE : MARCH 24, 2025 PC :
1.
Learned Counsel for the Respondent submits that the arbitration proceedings are already underway before the MSME Facilitation Council and therefore objects to allowing this application. 2.
Learned Counsel for the Applicant submits that the claim for which proceedings before the MSME Facilitation Council are underway is different from the claim for which this application has been filed. He seeks some time to take instructions as to which of the two forums would be pursued and whether the applicant would make an election on this subject. In these circumstances, stand over to April 7, 2025 under the same caption.
Digitally signed by AARTI GAJANAN PALKAR Date:
2025.03.29 11:19:35 +0530 AARTI GAJANAN PALKAR MARCH 24, 2025 Aarti Palkar
23.CARAP.271.2024.doc 3.
All actions required to be taken pursuant to this order, shall be taken upon receipt of a downloaded copy as available on this Court's website.
[ SOMASEKHAR SUNDARESAN, J.] MARCH 24, 2025 Aarti Palkar