← Library
Bombay High CourtCARBP/212/2024disposed off

Dharmadev Infrastructure Limited Through Its Authorised Representative Mr. Neel Thakkar v. Lok Holdings And Construction Limited Through Its Managing Director Mr. Darshan Gandhi

2024-08-28Hon'Ble Justice Shri Arif S. Doctor2 pages

9-CARBP-212-2024.DOC Shephali

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION COMMERCIAL ARBITRATION PETITION NO. 212 OF 2024 AND COMMERCIAL ARBITRATION APPLICATION (L) NO. 25194 OF 2024 (Not on Board) Dharmadev Infrastructure Limited Through Its

...Petitioner

Authorised Representative Neel Thakkar

Versus

Lok Holdings And Construction Limited Through Its

...Respondents

Managing Director Darshan Gandhi & Anr Mr Sanjeev Gorwadkar, Senior Advocate, with Pankaj Jay, Tanmay S, i/b PD Jain & Co, for the Petitioner.

Mr Ashish Pyasi, with Anjali Shahi, for Respondent No. 1. Mr Nikhil Wable, with Vinisha Bhwnani, i/b Jayakar & Partners, for SHEPHALI SANJAY MORMARE Respondent No. 2.

by SHEPHALI SANJAY MORMARE Date: 2024.08.29 10:01:01 +0530

CORAM:

ARIF S. DOCTOR, J DATED:

28th August 2024 PC:- 1.

Learned Counsel appearing on behalf of the Respondents today seek time to file Affidavit in Reply to the Petition under Section 9 and to

9-CARBP-212-2024.DOC the Application under Section 11 of the Arbitration and Conciliation Act 1996.

2.

Let that Affidavits in Reply be filed and served on or before 10th September 2024.

3.

Learned Counsel appearing on behalf of Respondent No. 1 states that in the event the Respondent No. 1 wants to create any third party rights in respect of the suit property, he shall give the Petitioner one week's prior notice of the same.

4.

List the matter on 19th September 2024.

(ARIF S. DOCTOR, J)