← Library
Bombay High CourtCARBP/274/2024disposed off

Tata Motors Finance Limited v. Project Equipments Construction Company And ANR

2026-02-04Hon'Ble Justice Shri Arif S. Doctor2 pages

1/2 10-CARBP-274-2024 (OS).DOC

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION COMMERCIAL ARBITRATION PETITION NO. 274 OF 2024 Tata Motors Finance Limited

...Petitioner

Versus

Project Equipments Construction Company And Anr

...Respondents

WITH INTERIM APPLICATION(L) NO. 26548 OF 2024 WITH COMMERCIAL ARBITRATION APPLICATION(L) NO. 27124 OF 2024 IN COMMERCIAL ARBITRATION PETITION NO. 274 OF 2024 _______ Mr. Gaurav Jangle a/w Akshita Jain a/w Akshit Vats i/b I.V. Merchant and Company for the Petitioner.

Mr. Neeraj Sekhar (Through VC), Mr. Pravin Singh i/b Ashok Singh for Respondents.

_______

CORAM

:

ARIF S. DOCTOR, J.

th FEBRUARY, 2026 DATE :

P.C.

1.

The matter was kept back at 3:00 p.m, as learned counsel appearing on behalf of the Respondent No.4 reported no instructions. 2.

At 3:00 p.m. Mr. Sekhar has appeared virtually and sought time. He submits that the details of all balance 8 vehicles shall be intimated to the Court. He also submits that the Respondents have taken out an Application for modification of the Order dated 14 th November, 2025, as it is the case of the Areeb

2/2 10-CARBP-274-2024 (OS).DOC Respondents that they have made full payment in respect of those 8 vehicles. Mr. Sekhar undertakes to file Vakalatnama.

th February, 2026. High on Board.

3.

Stand over to 6 [ARIF S. DOCTOR, J.] Areeb