IN THE HIGH COURT OF JUDICATURE AT BOMBAY

PURTI PRASAD PARAB ORDINARY ORIGINAL CIVIL JURISDICTION PURTI PRASAD PARAB Date: 2025.06.13 19:21:59 +0530 COMM. ARBITRATION PETITION NO. 433 OF 2025 ALONGWITH INTERIM APPLICATION (L) NO. 9775 OF 2024 IN COMM. ARBITRATION PETITION NO. 433 OF 2025 Gannon Dunkerley and Company Limited

...Petitioner

Versus

D2H Green Solutions Pvt. Ltd.

...Respondent

Mr. Vidit Kumat i/b Mr. Amir Arsiwala for the Petitioner. Advocate for the Respondent appeared but appearance not tendered.

CORAM

: SOMASEKHAR SUNDARESAN, J.

DATE : JUNE 9, 2025 PC :

1.

This Petition challenges the arbitral award passed by the MSME Facilitation Council. Consequently, it would be necessary for the Petitioner, as a condition precedent, to deposit 75% of the amount awarded. Learned Counsel for the Petitioner submits that he shall make such deposit within a period of one week from today. It is made clear that 75% amount is to be computed on the entire amount awarded which would include interest awarded in the arbitral award computed until today, i.e., June 9, 2025. 2.

Should such deposit be made by June 16, 2025 liberty to approach the Registry to demonstrate the deposit so that the matter can be placed for this Court's consideration on June 23, 2025. June 9, 2025 Purti Parab

92-CARBP-433-2025 @ IAL-9775-2024.doc 3.

All actions required to be taken pursuant to this order shall be taken upon receipt of a downloaded copy as available on this Court's website.

[ SOMASEKHAR SUNDARESAN, J.] June 9, 2025 Purti Parab