← Library
Bombay High CourtIA/165/2025dismissed

Ramakant Ramlakhan Tiwari v. Slum Rehabilitation Authority And 7 ORS.

2025-09-15Hon'Ble Shri Justice Farhan Parvez Dubash2 pages

8-osial165-2025.doc Sumedh

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION INTERIM APPLICATION NO.165 OF 2025 IN WRIT PETITION NO.5037 OF 022 Ramakant Ramlakhan Tiwari ... Applicant/Petitioner v/s.

Slum Rehabilitation Authority & Ors.

... Respondent _______________________ Mr. Atal Bihari Dubey a/w. Adv. Mohd. Riyaz i/by Adv. Prerna Kinkar for the Petitioner.

Ms. Sweta Shah i/by Abhijit P. Kulkarni for the Respondent-SRA. Ms. Jyoti V. Mhatre i/by Adv. Komal Punjabi for Respondent No.4BMC. Mr. Vijay D. Patil for Respondent No.5.

Ms. Noorain Patel i/by Diamondwala & Co. for Respondent No.6. _______________________ CORAM : KAMAL KHATA, J.

DATED : 15TH SEPTEMBER 2025.

P.C. :

1.

Learned Advocate for the Respondent No.5 volunteers to pay costs of Rs.2,000/- to the Petitioner for non-compliance of Order dated 11th August 2025. The said costs shall be paid on or before 17th September 2025.

2.

Subject to payment of afore stated costs, time to file reply is extended upto 17th September 2025.

1/2 Digitally signed by SUMEDH NAMDEO SONAWANE Date:

2025.09.16 09:09:55 +0530 SUMEDH NAMDEO SONAWANE

8-osial165-2025.doc 3.

List the matter on 6th October 2025.

4.

The Advocates for the Petitioner shall, within one week, serve their list of dates and events, written submissions, and relevant case law cited, which shall be structured as a point-wise reply to the opposing party's contentions. Within a week thereafter, the Respondent shall do the same. The exercise shall be completed by 22nd September 2025.

5.

Ad interim relief granted earlier, if any, to continue till the next date.

(KAMAL KHATA, J.) 2/2