Khusharav Builders Private Limited v. Nishit Yogendra Patel And 3 ORS.
10 IA 782-25.DOCX Tilak
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION INTERIM APPLICATION NO. 782 OF 2025 IN SUIT (L) NO. 24371 OF 2022 Khusharav Builders Private Limited ... Applicant/ Plaintiff
Versus
Nishit Yogendra Patel and ors ... Defendants ______________________________________________________ Ms.Esha Malik with Mr.Ritvij Kale, for the applicant. ______________________________________________________ CORAM : Jitendra Jain, J.
DATED : 25 September 2025 PC:- 1.
Leave to amend the prayer clause in the Interim Application. There is a delay in filing the application and for the reasons stated in paragraph nos.9 and 10, delay is condoned. Suit was dismissed for non-removal of the objection.
2.
The applicant has explained the reasons in the application and being satisfied, the order dismissing the Suit is recalled and the Suit is restored. Objections to be removed within four weeks from today. If the objections are not removed within four weeks from today, then the Suit will stand dismissed without recourse to the Court. Cost of Rs.25,000/- to be paid to Cama and Albless Hospital,
10 IA 782-25.DOCX Mahapalika Marg, Mumbai 400001 within a period of four weeks from today.
3.
Interim Application is disposed of.
(Jitendra Jain, J)