Samartha Development Corporation v. Municipal Corporation Of Greater Mumbai
901. IA 804-24 in EXAL 5358-24.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION INTERIM APPLICATION NO. 804 OF 2024 IN EXECUTION APPLICATION (L) NO. 5358 OF 2024 Samartha Development Corporation ...Applicant V/s.
Municipal Corporation of Gr. Mumbai
...Respondent
Mr. Danish Qureshi i/b Mahimtura and Co., Advocate for the Applicant/Judgment Creditor.
Mr. Govilkar, Senior Advocate with Ms. Jyoti Mhatre for the Respondent/BMC.
CORAM
:
ABHAY AHUJA, J.
DATE :
25th AUGUST, 2025 P.C. :
1.
This matter has been listed under the caption "For Compliance". 2.
When the matter is called out, Mr. Qureshi, learned Counsel appears for the Applicant and submits that the entire balance amount has been received and the Execution Application and the Interim Application be accordingly disposed of and the decree be marked as fully satisfied.
3.
Mr. Govilkar, learned Senior Counsel appears for the Respondent and submits that the entire balance amount has been paid and the Digitally signed by NIKITA YOGESH GADGIL Date:
2025.08.26 10:27:02 +0530 decree can be marked as fully satisfied.
NIKITA YOGESH GADGIL Nikita Gadgil 1/2
901. IA 804-24 in EXAL 5358-24.doc 4.
Having heard the learned Counsel and the learned Senior Counsel and having considered their submissions, this Court directs that in view of the payments having been received by the Applicant from the Respondent, the decree be marked fully satisfied. 5.
The Execution Application and the Interim Application accordingly stand disposed.