Bombay High CourtIA/1896/2025disposed off

Ms Sas Infra Projects India Pvt Ltd v. New Consolidated Construction Co Ltd

2025-07-21Hon'Ble Shri Justice Abhay Ahuja1 pages

Board Sr.No.:-37

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION INTERIM APPLICATION NO. 1825 OF 2025 In COMMERCIAL SUIT 122 OF 2016 Sas Infra Projects India Pvt Ltd ....PETITIONER V/S New Consolidated Construction Co Ltd ....RESPONDENT WITH INTERIM APPLICATION NO. 1896 OF 2025 In Commercial Suit 117 OF 2016 Ms Sas Infra Projects India Pvt Ltd ....PETITIONER V/S New Consolidated Construction Co Ltd ....RESPONDENT CORAM :

HON'BLE SHRI JUSTICE ABHAY AHUJA J DATE :

21st July, 2025 P.C. :

Balance Daily Board cannot be taken up today on account of paucity of time. Stand over to 08/09/2025 . Ad-interim relief or interim relief, if any, granted earlier will continue to operate till next date.