← Library
Bombay High CourtWP/2003/2025disposed off

Shree Chhatrapati Shivaji Foundation Society Dharwad Throu. Its President And ANR v. The State Of Maharashtra Throu.The Sec. And ANR

2025-02-13Hon'Ble Shri Justice Jitendra Shantilal Jain , Hon'Ble Shri Justice M.S. Sonak2 pages

1 911 wp-2003-25 .doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION BHARAT DASHARATH PANDIT BHARAT DASHARATH PANDIT Date: 2025.02.13 16:55:32 +0530 WRIT PETITION NO. 2003 OF 2025 Shree Chhatrapati Shivaji Education Society, Dharwad Through its President and Another ... Petitioners V/s State of Maharashtra Through its Secretary and Others ....Respondents.

Mr. R.V. Pai, Senior Advocate a/w Ms. Bina Pai a/w Mr. Akshay Pai & Ms. Siddhi Bhosale, Advocates for the petitioners. Mr. Anil C. Singh, Senior Advocate a/w Mr. Pankaj S. Deokar, Advocates for respondent no.2 - Zilla Parishad, Satara. Mr. N.C. Walimbe, Additional Government Pleader a/w Mrs. R.A. Salunkhe, Assistant Government Pleader for the respondent no.1-State. **** CORAM :

A. S. CHANDURKAR & M. M. SATHAYE, JJ.

DATE : 13th FEBRUARY 2025 P.C. :

1] We have heard the learned counsel for the parties for sometime. It is seen from the record that pursuant to the directions issued by this Court in Writ Petition No.12833 of 2024 on 29/11/2024 requiring the petitioners to take steps to obtain the final fire NOC from the competent authority by 31/12/2024, an inspection of the hospital was undertaken on 25/12/2024. On 26/12/2024, the Divisional Fire Officer, Maharashtra Industrial Development Corporation issued a communication to the petitioners requiring them to take steps and remove the named deficiencies to enable issuance of the final fire NOC. BDP-SPS 1/2

2 911 wp-2003-25 .doc According to the learned Senior Advocate for the petitioners, insofar as item no.2 in the said communication is concerned steps are underway to comply with the same. He submits that insofar as other shortcomings are concerned, the same had been complied with. 2] Leave granted to implead the Divisional Fire Officer, MIDC Hinjewadi, Pune as respondent no.3. Amendment be carried out forthwith. Thereafter, issue notice to the said respondent making it returnable on 21/02/2025. In the meanwhile, the Fire Officer shall inspect the hospital building and file an affidavit indicating whether necessary compliance of item nos. 1 and 3 to 6 has been done by the petitioners.

3] List under the caption "For directions" on 21/02/2025. 4] Parties to act on the authenticated copy of this order. (M. M. SATHAYE, J.) (A. S. CHANDURKAR, J.) BDP-SPS 2/2