← Library
Bombay High CourtWP/4979/2025disposed off

Maharashtra State Electricity Distribution Company Limited v. The State Of Maharashtra Through Its Chief Electrical Inspector And Another

2025-04-24Hon'Ble Shri Justice Kishore C. Sant2 pages

2025:BHC-AUG:12099 1 904-wp 4979-2025.odt

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD WRIT PETITION NO. 4979 OF 2025 Maharashtra State Electricity Distribution Company Limited Through its Executive Engineer Prashant Ramashray Sonar .. Petitioner

Versus

The State Of Maharashtra Through Its Chief Electrical Inspector And Another .. Respondents Mr. Anil S. Bajaj, Advocate for the Petitioner. Mr. P. D. Patil, AGP for Respondent/State.

CORAM :

KISHORE C. SANT, J.

DATED : 24th APRIL, 2025.

P. C. :- .

Heard for some time.

2.

An order challenged in this petition is only a communication by the Electrical Inspector, Jalna to the Executive Engineer, MSEDCL, Jalna, Division - 1. The communication is in respect of untoward incident that took place where a person received an injury by coming in contact of line of tension of the MSEDCL. The Electrical Inspector conducted inspection and on the same basis communicated that the petitioner - company is liable to pay the compensation to the said person.

2 904-wp 4979-2025.odt 3.

This Court finds that, this is not an order passed by quasi judicial or judicial authority and it is a simple communication. This Court, thus, finds that, this petition is not maintainable. The writ petition, therefore, is dismissed by keeping liberty open to the petitioner to avail alternative remedy if provided under law.

( KISHORE C. SANT, J. ) P.S.B.