Reliance Asset Reconstruction Company Limited v. State Of Maharashtra Thr The Ld Executive Magistrate And ORS

2025-12-24Hon'Ble Shri Justice R. I. Chagla , Hon'Ble Shri Justice Farhan Parvez Dubash2 pages

Reliance Asset Reconstruction Co. Ltd. Vs. State 917.WP/8475/2025

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION WRIT PETITION NO. 8475 OF 2025 Reliance Asset Reconstruction Co. Ltd ... Petitioner V/s.

State of Maharashtra (through District Magistrate) & Ors.

... Respondents _______________________________________ Mr. Daneel Pancras i/b. Archit Virmai for the Petitioner. Dr. Dhruti M. Kapadia, learned AGP for State. _______________________________________ CORAM : R.I. CHAGLA AND FARHAN P. DUBASH, JJ.

DATE :

24th DECEMBER 2025 ORDER :

1.

By this Petition the Petitioner is seeking directions to Respondent No. 1 to forthwith remove trespassers from the Secured Asset of the Petitioner which was in physical possession of the Petitioner in execution of the earlier order dated 4th February 2022 read with order dated 8th September 2023 passed by Respondent No. 2 and to take further steps in handing over the vacant and physical possession of the said Secured Asset to the Petitioner in time bound manner.

------------------------------------- Order dated 24th December 2025

Reliance Asset Reconstruction Co. Ltd. Vs. State 917.WP/8475/2025 2.

The learned AGP appearing for the State on instructions states that the Respondent - State will issue the possession notice on or before 15th January 2026 and physical possession of the Secured Asset will be taken on or before 31st January 2026. The statement is accepted. 3.

The Respondent No. 4 - learned Inspector of Police, Warje Malwadi Police Station, Pune shall provide necessary police assistance for taking of physical possession of the Secured Asset on the scheduled date. 4.

The Respondent Nos. 3 to 5 shall also render necessary assistance to the Respondent No. 1 in taking of physical possession of the Secured Asset by the scheduled date.

6.

The Writ Petition is accordingly disposed of. No order as to costs. 7.

Place the Writ Petition for compliance on 2nd February 2026. [FARHAN P. DUBASH, J.] [R.I. CHAGLA, J.] Ajay Jadhav 917.WP/8475/2025 by JYOTI PRAKASH PAWAR Date:

2025.12.24 21:39:03 +0530 JYOTI PRAKASH PAWAR ------------------------------------- Order dated 24th December 2025