Bombay High CourtWP/13592/2025allowed to be withdrawn

Roma Builders Private Limited v. State Of Maharashtra

2025-10-15Hon'Ble Shri Justice A.S. Gadkari , Hon'Ble Shri Justice Shyam C. Chandak2 pages

503 TO 506-WP-13589-25 & ORS.DOC JYOTI RAJESH MANE

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION by JYOTI RAJESH MANE Date: 2025.10.17 11:02:26 +0530 WRIT PETITION NO. 13589 OF 2025 Roma Builders Private Limited

...Petitioners

Versus

State Of Maharashtra Through The Revenue Department

...Respondents

WITH WRIT PETITION NO. 13590 OF 2025 Roma Builders Private Limited

...Petitioners

Versus

State Of Maharashtra Through The Revenue Department

...Respondents

WITH WRIT PETITION NO. 13591 OF 2025 Roma Builders Private Limited

...Petitioners

Versus

State Of Maharashtra Through Revenue Department

...Respondents

WITH WRIT PETITION NO. 13592 OF 2025 Roma Builders Private Limited

...Petitioners

Versus

State Of Maharashtra

...Respondents

_______ Mr. Shardul Singh a/w. Ms. Prerna Gandhi a/w. Mr. Ninad Thikekar a/w. Ketul Bhandari i/b. SHS Chambers, for Petitioners. Smt. M. P. Thakur, AGP for Respondent Nos.1 to 3 in WP/13589/25. Mr. Y. D. Patil, AGP for Respondent Nos. 1 to 3 in WP/13590/25. Smt. S.A.Prabhune, AGP for Respondent Nos.1 to 3 in WP/13591/25. Dr. Dhruti Kapadia, AGP for Respondent Nos. 1 to 3 in WP/13592/25. _______ Mane

503 TO 506-WP-13589-25 & ORS.DOC

CORAM:

G. S. KULKARNI & AARTI SATHE, JJ.

DATE:

15th October 2025 P.C.

1. Not on board. Taken on board.

2. List the present petitions alongwith the batch of petitions viz. WP/13123/25 and other petitions, on which this Court has passed an Order on 7th October 2025.

3. Let the reply affidavit be filed within a period of three weeks from today.

4. In the event the coercive steps are required to be taken an advance notice of 48 working hours be issued by the Respondents to the Petitioner. 5.

Stand over to 12th November 2025.

(AARTI SATHE, J.) (G. S. KULKARNI, J.) Mane