Sarika Bhagwanrao Renguntwar v. Joint Director Higher And Technical Education And Others
2026:BHC-AUG:2987-DB
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 927 WRIT PETITION NO.15095 OF 2025 SARIKA BHAGWANRAO RENGUNTWAR
VERSUS
JOINT DIRECTOR HIGHER AND TECHNICAL EDUCATION AND OTHERS ...
Mr. Ramraje Deshmukh, Advocate h/f Mr. S.V. Deshmukh, Advocate for petitioner Mr. V.M. Kagne, AGP for respondent No.1 ...
CORAM :
SMT. VIBHA KANKANWADI & HITEN S. VENEGAVKAR, JJ.
DATE :
22nd JANUARY, 2026 ORDER :
.
Present petition has been filed for directions to respondent No.1 to grant, approve and release the consequential benefits a/w interest of CASAL-14 Stage promotion to petitioner as per the approval issued by respondent No.3 - University, within a period 15 days.
Learned AGP waives notice for respondent No.1. Since the matter is pending before respondent No.1, upon instructions, learned AGP submits that the said proposal would be decided within a period of eight weeks. We take the said statement as undertaking and dispose of the writ petition by directing respondent No.1 to decide the said proposal within a period of eight weeks.
( HITEN S. VENEGAVKAR, J. ) ( SMT. VIBHA KANKANWADI, J. ) agd