IN THE HIGH COURT OF JUDICATURE AT BOMBAY

varsha CIVIL APPELLATE JURISDICTION APPEAL FROM ORDER NO. 341 OF 2025 Mukesh Ramesh Bajaj ... Appellant vs.

Brihanmumbai Municipal Corporation and Anr ... Respondents Ms.Pratibha Shelake a/w. Ms. Babita Kesharwani i/b. K. Amol for Appellant.

Mr. Om Suryavanshi i/b. Ms. Komal Punjabi for Respondent-BMC. CORAM : GAURI GODSE, J.

DATED : 30th JUNE 2025 ORDER:

1.

Not on board. Taken on production board.

2.

This petition is circulated on behalf of the corporation for correction in paragraph no.2 in order dated 23rd June 2025. 3.

Learned counsel for the corporation submits that the undertaking tendered on behalf of the appellant was for removal of the offending structure within three weeks. However, in paragraph no.2, inadvertently, it is recorded as 'three months'. 4.

Learned counsel for the appellant has no objection for such correction. Order dated 23rd June 2025 be corrected by replacing Page no. 1 of 2

508-ao-341-2025.doc the word 'months' with the word 'weeks' in 9th line of paragraph no. 2.

5.

Original order be corrected and corrected order to be uploaded.

(GAURI GODSE, J.) Page no. 2 of 2