The Executive Engineer Waghur Dam And ANR v. Thecollector, Jalgaon And ORS
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 28 CIVIL APPLICATION NO. 81 OF 2025 IN FAST/274/2025 WITH CIVIL APPLICATION NO. 83 OF 2025 IN FAST/274/2025 WITH CIVIL APPLICATION NO. 84 OF 2025 IN FAST/279/2025 WITH CIVIL APPLICATION NO. 85 OF 2025 IN FAST/279/2025 The Executive Enginerr Waghur Dam And Anr
VERSUS
The Collector Jalgaon And Ors AND 29 CIVIL APPLICATION NO. 86 OF 2025 IN FAST/260/2025 WITH CIVIL APPLICATION NO. 87 OF 2025 IN FAST/260/2025 WITH CIVIL APPLICATION NO. 88 OF 2025 IN FAST/263/2025 WITH CIVIL APPLICATION NO. 89 OF 2025 IN FAST/263/2025 The Executive Engineer Waghur Dam And Anr
VERSUS
The Collector, Jalgaon And Ors ...
AND 30 CIVIL APPLICATION NO. 90 OF 2025 IN FAST/300/2025 WITH CIVIL APPLICATION NO. 91 OF 2025 IN FAST/300/2025 WITH CIVIL APPLICATION NO. 92 OF 2025 IN FAST/303/2025 WITH CIVIL APPLICATION NO. 93 OF 2025 IN FAST/303/2025 WITH
CIVIL APPLICATION NO. 94 OF 2025 IN FAST/307/2025 WITH CIVIL APPLICATION NO. 95 OF 2025 IN FAST/307/2025 The Executive Engineer, Waghur Dam Division Jalgaon And Anr
VERSUS
The Collector Jalgaon And Ors Advocate for Applicant : Mr. V V Tarde AGP for Respondents: Mr. D B Bhange Mr. B.K. Pawar h/f Mr. A.B. Kale for respondents/claimants. (in all applications) CORAM : S. G. CHAPALGAONKAR, J.
Dated : January 06, 2025 ORDER :- (Delay condonation application) 1.
Heard.
2.
Issue notice to the Respondents, returnable on 3.3.2025. Learned AGP waives notice for respondent no.1. Advocate Mr. B.K. Pawar h/f Mr. A.B. Kale waives notice for respondents /claimants.
Stay Application :- 1.
Heard learned advocates appearing for the respective parties.
2.
Having considered the submissions advanced, there shall be ad-interim stay to the judgment and award under challenge subject to condition that the applicant deposits entire awarded
amount with the Registry of this Court / Reference Court within a period of eight (8) weeks from today. ( S. G. CHAPALGAONKAR, J. ) aaa-