IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 11 CIVIL APPLICATION NO. 3559 OF 2025 IN FAST/6833/2025 WITH CIVIL APPLICATION NO. 3558 OF 2025 IN FAST/6833/2025 WITH CIVIL APPLICATION NO. 3566 OF 2025 IN FAST/6844/2025 WITH CIVIL APPLICATION NO. 3567 OF 2025 IN FAST/6844/2025 THE EXECUTIVE ENGINEER CENTRAL RAILWAY PUNE AND ORS

VERSUS

RAJARAM BHAGUJI DESAI AND ANR ...

12 CIVIL APPLICATION NO. 7189 OF 2025 IN FAST/20312/2025 WITH CIVIL APPLICATION NO. 7191 OF 2025 IN FAST/20312/2025 ...

13 CIVIL APPLICATION NO. 10728 OF 2025 IN FAST/22986/2025 WITH CIVIL APPLICATION NO. 10729 OF 2025 IN FAST/22986/2025

CORAM

: SHAILESH P. BRAHME, J.

DATE : 01.04.2026 PER COURT :

1.

Time of four (4) weeks is granted to take steps against the dead respondents as well as unserved respondents.

2.

In case, fresh address is provided for the service of notice, then notice shall be issued, returnable after four (4) weeks. 3.

In case for some technical reasons, the notices are unserved, re-issue 1/2

11 to 13 CA 3559 OF 2025+.odt notice to the unserved respondents, returnable four (4) weeks thereafter. 4.

In case of remark of want of time, the time is extended by four (4) weeks.

5.

Interim relief, granted earlier, if any, to continue till the next date. 6.

Humdast/private service is permitted.