Tapi Irrigation Development Corporation Jalgaon Through The Executive Engineer v. The State Ofmaharashtra Through The Collector Jalgaon And ORS
24-ca-4705-2025.odt (1)
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 4705 OF 2025 IN FAST/12699/2025 WITH CIVIL APPLICATION NO. 4706 OF 2025 IN FAST/12699/2025 Tapi Irrigation Development Corporation Jalgaon Through The Executive Engineer
VERSUS
The State Ofmaharashtra Through The Collector Jalgaon And Ors ...
Advocate for Applicant : Mr. Shivraj B Kadu AGP for Respondent/State : Mr. D.B. Bhange ...
CORAM : S.G. CHAPALGAONKAR, J.
DATED : APRIL 30, 2025 PER COURT :
1.
Heard.
2.
Issue notice to respondents, returnable after twelve weeks. Learned AGP waives notice for respondent nos.1 and 2. In Stay Application :
3.
Heard.
4.
Issue notice to respondents, returnable after twelve weeks. Learned AGP waives notice for respondent nos.1 and 2. 5.
Till then, there shall be ad-interim stay to the judgment and award under appeal subject to condition that the applicant deposits entire awarded amount with the registry of this Court by returnable date.
(S.G. CHAPALGAONKAR, J.) Mujaheed//