← Library
Bombay High CourtCA/6481/2025admittedallowedgrantedrule absolute

Zumbarbai W/O Pralhad Gaikwad And ORS v. The Executive Engineer, Minor Irrigation Wwrk M I Division No 1 And ORS

2025-08-04Hon'Ble Shri Justice Shailesh P. Brahme1 pages

1 119 ca 6481.25

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO. 6481 OF 2025 IN FIRST APPEAL NO. 2371 OF 2024 Zumbarbai W/o Pralhad Gaikwad and others

VERSUS

The Executive Engineer, Minor Irrigation Work M I Division No 1 and others Shri Dinkar G. Kamble, Advocate for the Applicants. Ms. Vaishali S. Swami, Advocate h/f Shri Mahesh C. Swami, Advocae for the Respondent No. 1.

Shri D. B. Bhange, A.G.P. for the Respondent No. 2. Shri P. S. Paranjape, Advocate for the Respondent No. 4. CORAM : SHAILESH P. BRAHME, J.

DATE : 04TH AUGUST, 2025.

ORDER :

.

Learned counsel for the respondent No. 4 seeks time to file reply. As a last indulgence time of two (02) weeks is granted. To be placed in the same category.

[ SHAILESH P. BRAHME J. ] bsb/Aug. 25