New India Assurance Co Ltd Through Its Manager v. Dadasaheb Raybhan Sathe And Others
934 CA NO. 11315 OF 2025.odt
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD 934 CIVIL APPLICATION NO. 11315 OF 2025 IN FAST/30311/2025 New India Assurance Co Ltd Through Its Manager
VERSUS
Dadasaheb Raybhan Sathe And Another ...
Mr. Deshmukh Mohit Rameshrao, Advocate for Applicant Mr. Badakh Vishal S., Advocate for Respondent No.1 WITH CIVIL APPLICATION NO. 11316 OF 2025 IN FAST/30311/2025 ....
CORAM : SANJAY A. DESHMUKH, J.
DATE : 10.02.2026 PER COURT :- APPLICATION FOR DELAY 1.
Heard.
2.
This is an application for condonation of delay of 26 days caused in filing the first appeal.
3.
Learned advocate for respondent No.1 strongly opposed the application.
4.
Perused the application. For the reasons stated therein, the application deserves to be allowed in the interest of justice as the delay is neither deliberate nor intentional. Hence, the following order:
(( 2 )) 934 CA NO. 11315 OF 2025 ::ORDER::
a.
Civil Application is allowed.
b.
The delay of 26 days caused in filing the first appeal is hereby condoned.
c.
The application is disposed of.
FIRST APPEAL .
Issue notice to the respondents, returnable on 05.05.2026. 2.
Mr. Vishal S. Badakh, learned Advocate waives service of notice for Respondent No.1.
APPLICATION FOR STAY 1.
This is an application seeking stay to the execution of the impugned judgment and award.
2.
The learned advocate for the applicant / appellant submits that the entire amount as per the impugned judgment and award is deposited in this Court.
3.
In view of the above, there shall be stay to the impugned judgment and award till the pendency of the appeals. The applications are disposed of.
[ SANJAY A. DESHMUKH, J. ] HRJadhav