IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CONTEMPT PETITION NO.504 OF 2025 WITH WRIT PETITION NO. 3801 OF 2019 Anna Tatoba Borgave .....Petitioner Vs.

The State of Maharashtra .....Respondent Mr. Umesh H. Pawar, for the Petitioner.

Smt. S. D. Vyas, Additional Government Pleader with Smt. Pooja Joshi Deshpande, AGP for the Respondent-State.

Mr. Vikram Walawalkar, with Mr. Amey C. Sawant, for the Respondent Nos.4 & 5.

CORAM : REVATI MOHITE DERE & DR. NEELA GOKHALE, JJ.

DATE : 05th AUGUST 2025.

P.C.:- 1.

Since, the Registry has not placed before us the papers of the aforesaid Contempt Petition, we are unable to proceed with the hearing of the same.

2.

Even otherwise, the learned counsel appearing for the Respondent-Corporation, on instructions, states that the process of apportionment will be completed within four weeks from today. Statement accepted.

Shivgan 1/2

18-cp-504-2025.doc 3.

Stand over to 2nd September 2025.

4.

In the meantime, we grant liberty to the learned counsel for the Petitioner to amend the Petition. Leave granted. Amendment to be carried out within one week.

5.

A copy of the amended Petition also to be served on the learned counsel appearing for the Respondents. 6.

We are constrained to observe that if the order dated 18th February 2025 is not complied with before the next date, we would be constrained to take appropriate steps in accordance with law. (DR. NEELA GOKHALE, J.) (REVATI MOHITE DERE, J.) Digitally signed by SHAMBHAVI NILESH SHIVGAN Date:

2025.08.07 11:00:05 +0530 SHAMBHAVI NILESH SHIVGAN Shivgan 2/2