← Library
Bombay High CourtARP/136/2025disposed off

Cosmos Buildersa Partnership Firm Through Its Partner Manish G Mehta v. Arjun Sitaram Nitinwar

2025-06-17Hon'Ble Shri Justice Somasekhar Sundaresan1 pages

514-ARP-136-2025 copy.docx

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

PURTI PRASAD PARAB CIVIL APPELLATE JURISDICTION PURTI PRASAD PARAB Date: 2025.06.20 17:34:09 +0530 ARBITRATION PETITION NO. 136 OF 2025 Cosmos Builders

...Petitioner

Versus

Arjun Sitaram Nitinwar

...Respondent

Mr. Jayesh Madhav Joshi for the Petitioner.

None for the Respondent.

CORAM

: SOMASEKHAR SUNDARESAN, J.

DATE : JUNE 17, 2025 ORDER :

1.

This is a Petition under Section 29-A of the Arbitration and Conciliation Act, 1996, seeking an extension of mandate of the Arbitral Tribunal, which expired on February 18, 2025. 2.

It is seen from the Minutes of Meeting held on February 18, 2025 that the parties were well aware that this request for extension would be necessary.

3.

In these circumstances, taking into account the stage at which the Arbitral proceedings are placed, this Petition is finally disposed of extending the mandate of the Arbitral Tribunal for a period of one year rounded up until June 30, 2026.

4.

All actions required to be taken pursuant to this order shall be taken upon receipt of a downloaded copy as available on this Court's website.